摘要
This paper considers a problem of uniform-machine scheduling with machine release times to minimize makespan. Firstly, four properties of swapping jobs are proposed. Then, based on the properties, a heuristic algorithm is presented, which takes the LPT schedule as its initial solution and improves the solution by repeatedly swapping the jobs between two machines with the maximal and minimal makespan. Finally, computational results show that the presented heuristic is efficient and effective.
| 源语言 | 英语 |
|---|---|
| 页(从-至) | 2022-2030 |
| 页数 | 9 |
| 期刊 | Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice |
| 卷 | 32 |
| 期 | 9 |
| 出版状态 | 已出版 - 9月 2012 |
| 已对外发布 | 是 |