Convex resource allocation scheduling in the no-wait flowshop with common flow allowance and learning effect

  • Shenyang Aerospace University
  • Dongbei University of Finance and Economics

科研成果: 期刊稿件文章同行评审

34 引用 (Scopus)

摘要

We study the problem of two-machine no-wait flowshop scheduling with learning effect and convex resource-dependent processing times. Under the condition of the due-date assignment with common flow allowance (i.e. slack (SLK) due-date assignment), we provide a bi-criteria analysis where the first criterion is to minimise the scheduling criteria (i.e. the weighted sum of earliness, tardiness and flow allowance costs), and the second criterion is to minimise the resource consumption cost (i.e. the weighted sum of resource consumption cost). The objective is to determine the optimal job sequence, resource allocations and common (flow allowance) slack time that minimise the three different versions of the two criteria. We prove that these problems can be solved in polynomial time.

源语言英语
页(从-至)1873-1891
页数19
期刊International Journal of Production Research
57
6
DOI
出版状态已出版 - 19 3月 2019

学术指纹

探究 'Convex resource allocation scheduling in the no-wait flowshop with common flow allowance and learning effect' 的科研主题。它们共同构成独一无二的指纹。

引用此