摘要
This paper proposes a novel unit maintenance scheduling (UMS) model, considering the influence of unexpected unit failures. The uncertain factor not only leads to costly expenditure for replacing the damaged components, but also lowers the system reliability and increases the operation cost. This is rarely considered or is often simplified as a constant value in the existing approaches. Based on the generator's bath-curve failure model and the corresponding renewable costs, the impacts of scheduling outage and unexpected failures on the operational costs are discussed in detail. The reliability costs and generation costs of the system, and the renewable costs and maintenance costs of generating units are included in the operational costs analysed. The former two costs are calculated through the system probabilistic production simulation by equivalent energy function (EEF) method. Subsequently, the UMS model is presented to minimize the total costs over the whole planning horizon, which is solved by a genetic algorithm because of its non-linear and non-differentiable characteristics. Finally, numerical examples based on a 21-unit system are utilized to demonstrate the usefulness of the proposed scheme. This work is jointly supported by Special Fund of the National Priority Basic Research of China (No. 2004CB217905) and National Natural Science Foundation of China (No. 50677050).
| 源语言 | 英语 |
|---|---|
| 页(从-至) | 32-36 |
| 页数 | 5 |
| 期刊 | Dianli Xitong Zidonghua/Automation of Electric Power Systems |
| 卷 | 33 |
| 期 | 13 |
| 出版状态 | 已出版 - 10 7月 2009 |
联合国可持续发展目标
此成果有助于实现下列可持续发展目标:
-
可持续发展目标 7 经济适用的清洁能源
学术指纹
探究 'A generator maintenance scheduling model considering unexpected unit failures' 的科研主题。它们共同构成独一无二的学术指纹。引用此
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver