不同业主支付方式下基于鲁棒性阈值的净现值最大化项目调度优化

  • College of Economics and Management
  • Qingdao University of Science and Technology
  • Xi’an Jiaotong University
  • School of Economics and Management
  • China University of Petroleum (East China)
  • Zhengzhou College of Finance and Economics

科研成果: 期刊稿件 › 文章 › 同行评审

1 引用 (Scopus)

摘要

In practical project management, there exist many uncertain factors, such as weather changes, shortage of resource supply, untimely capital payment, may influence the activity duration and the contractor's cash flow arrangement during the whole project implementation process, and finally cause the loss of project profit. At the meanwhile, different clients payment modes determine the time and scales of cash inflow, the project contractor optimizes the arrangement of project activities and cash outflow according to the cash inflow by client, so as to ensure the smooth implementation and completion of the project. Therefore, it has a very important guiding significance for the optimal scheduling and management of cash flow of the actual project, and how to choose a reasonable client payment mode while dealing with the interference of uncertainty factors so that the project can obtain the maximum benefit.Considering the impact of the clients payment modes on project cash flow distribution and profit under uncertain environment, the robust Max-NPV project scheduling optimization problem is studied on different clients payment modes, where time buffer strategy is applied to strengthen the baseline schedule robustness, and at the same time the robustness threshold constraint is formulated. Firstly, the research problem is defined, and on basis of the robustness threshold, a two-stage project payment Max-NPV scheduling optimization model under different payment modes (progress-based, cost-based, time-based, milestone-based) is constructed; The first stage is a robustness maximization scheduling model, to obtain the maximal robustness value and solve the resource constraint based on the resource flow network, and the second stage is to solve the Max-NPV optimization problem under the given robustness threshold constraint. Then, according to the NP-hard property of the problem, a tabu search heuristic algorithm is designed, and considering the algorithms' neighborhood quantity and search strategy on performance, the variable neighborhood heuristics, multi-start iteration improvement and random generation algorithms are adopted as benchmarks. The four algorithms are tested on a set of randomly generated large scall standard instances, and moreover, the sensitivity of key parameters on project net present value is analyzed.The conclusions of the research are as follows. Firstly, compared with the four algorithms, the designed tabu search algorithm performs better other three algorithms with acceptable time. Then, compared with the four clients payment modes with different algorithms, the results show that different payment modes have an important impact on the contractor's project net present value, among which, the progress-based payment mode performs the best, and the cost-based and milestone-based rank the second, while the time-based payment mode is the worst. Moreover, the influences of the key parameters including the payment numbers, the project deadline, the payment proportion, the discount rate, the buffer cost per unit time, the robustness threshold coefficient on the project net present value are analyzed, and the following results are drawn: the contractor's net present value increases with the increase of the client payment numbers and the payment proportion, and decreases with the increase of the discount rate, the buffer cost per unit time and the robustness threshold coefficient, and first rises and then decreases with the increase of the project deadline. It is more important to note that, a reasonable robustness threshold can increase the project's net present value, but too high or too small may induce a decrease conversely.The research in this paper can help project managers to determine the optimal payment strategy and schedule under uncertainty environment, ensuring the smooth implementation and the best benefits of the project. Therefore, it can provide effective decision supports for project scheduling of maximizing the net present value in reality.

投稿的翻译标题Robustness Threshold-based Max-NPV Project Scheduling Optimization on Different Clients' Payment Modes
源语言繁体中文
页(从-至)185-196
页数12
期刊Chinese Journal of Management Science
卷33
期4
DOI
出版状态已出版 - 25 4月 2025
已对外发布是

关键词

  • different payment modes
  • heuristic algorithms
  • Max-NPV project scheduling
  • optimization model
  • robustness threshold