The Proactive Resource-Constrained Project Scheduling Problem with Resource Transfer Times

Research output: Chapter in Book/Report/Conference proceedingConference contributionpeer-review

3 Scopus citations

Abstract

In this paper, we investigate the resource-constrained project scheduling problem with resource transfer times under uncertain environment, aiming to generate robust baseline schedules that will be as stable as possible during project execution. In this problem, resource transfer times are taken into account, and the objective function is solution robustness maximization. As the problem is proved to be NP-hard in the strong sense, we develop a tabu search algorithm to solve the problem. After linearizing the proposed model, we use a commercial mathematical programming solver as a benchmark to solve the problem. From the computational results, we find that the developed tabu search algorithm is effective and efficient in solving the defined problem, which offers a way to deal with the proactive scheduling problem with resource transfer times. Through a sensitivity analysis, we find that robustness increases with the extension of the project due date and the decrease of resource transfer times.

Original languageEnglish
Title of host publicationProceedings of the 2019 International Conference on Industrial Engineering and Systems Management, IESM 2019
EditorsFeifeng Zheng, Feng Chu, Ming Liu
PublisherInstitute of Electrical and Electronics Engineers Inc.
ISBN (Electronic)9781728115665
DOIs
StatePublished - Sep 2019
Event2019 International Conference on Industrial Engineering and Systems Management, IESM 2019 - Shanghai, China
Duration: 25 Sep 201927 Sep 2019

Publication series

NameProceedings of the 2019 International Conference on Industrial Engineering and Systems Management, IESM 2019

Conference

Conference2019 International Conference on Industrial Engineering and Systems Management, IESM 2019
Country/TerritoryChina
CityShanghai
Period25/09/1927/09/19

Keywords

  • proactive project scheduling
  • resource transfer times
  • solution robustness
  • tabu search