title = "Proactive Project Scheduling Optimization Based on Flexible Resource Constraint",
abstract = "The robustness of project schedule plays an important role for the smooth execution of project under uncertain conditions. This paper studies the proactive project scheduling problem with stochastic activity durations and flexible resource constraints. The objective is to schedule the starting times of the activities in a reasonable way so as to maximize the robustness of project schedule under the constraints of precedence, flexible resources and project deadline. The studied problem is defined at first. Then the optimization model is constructed. Based on the NP-hardness attribute of the problem and the characteristics of the model, a two-layer nested tabu search heuristic algorithm and a new heuristic algorithm are developed to obtain satisfactory solutions. Ultimately, algorithms are tested on a standard instance set generated randomly and the influences of the key parameters are analyzed.",
keywords = "flexible resource, optimization model, proactive project scheduling, stochastic activity duration, tabu search algorithm",
author = "Yong Ma and Zhengwen He and Nengmin Wang",
note = "Publisher Copyright: {\textcopyright} 2019 IEEE.; 2019 International Conference on Industrial Engineering and Systems Management, IESM 2019 ; Conference date: 25-09-2019 Through 27-09-2019",
year = "2019",
month = sep,
doi = "10.1109/IESM45758.2019.8948104",
language = "英语",
series = "Proceedings of the 2019 International Conference on Industrial Engineering and Systems Management, IESM 2019",
publisher = "Institute of Electrical and Electronics Engineers Inc.",
editor = "Feifeng Zheng and Feng Chu and Ming Liu",
booktitle = "Proceedings of the 2019 International Conference on Industrial Engineering and Systems Management, IESM 2019",
}