TY - GEN
T1 - Optimal unit maintenance scheduling of a power prouducer under price uncertainty
AU - Feng, Changyou
AU - Wang, Xifan
AU - Chen, Haoyong
PY - 2009
Y1 - 2009
N2 - This paper presents a day-based stochastic unit maintenance scheduling (UMS) model for a power producer in a pool-based power market. Its objective is to maximize the producer's benefit over the entire scheduling periods, with emphasis on potential risk associated with the fluctuating electricity prices. In the proposed model, the producer's potential benefit is analyzed in detail, mainly including the expected energy-selling profits in energy market and maintenance cost in each period. In order to evaluate the related risk resulted from the uncertain energy prices, a framework for the Latin Hypercube Sampling Monte Carlo simulation (LHS-MC) is adopted, which outperforms the ordinary Monte Carlo method. Then, the proposed stochastic UMS formulation can be solved using a combination of genetic algorithms and linear programmings. Finally, numerical examples on a four-unit producer are utilized to demonstrate the usefulness of the proposed scheme. Simulation results suggest that the uncertain market prices may lead to high risk on producer's outage planning and should be considered in producer's maintenance scheduling.
AB - This paper presents a day-based stochastic unit maintenance scheduling (UMS) model for a power producer in a pool-based power market. Its objective is to maximize the producer's benefit over the entire scheduling periods, with emphasis on potential risk associated with the fluctuating electricity prices. In the proposed model, the producer's potential benefit is analyzed in detail, mainly including the expected energy-selling profits in energy market and maintenance cost in each period. In order to evaluate the related risk resulted from the uncertain energy prices, a framework for the Latin Hypercube Sampling Monte Carlo simulation (LHS-MC) is adopted, which outperforms the ordinary Monte Carlo method. Then, the proposed stochastic UMS formulation can be solved using a combination of genetic algorithms and linear programmings. Finally, numerical examples on a four-unit producer are utilized to demonstrate the usefulness of the proposed scheme. Simulation results suggest that the uncertain market prices may lead to high risk on producer's outage planning and should be considered in producer's maintenance scheduling.
KW - Fluctuating electricity price
KW - LHS-Monte Carlo method
KW - Power market
KW - Unit maintenance scheduling
UR - https://www.scopus.com/pages/publications/70349190381
U2 - 10.1109/PSCE.2009.4839970
DO - 10.1109/PSCE.2009.4839970
M3 - 会议稿件
AN - SCOPUS:70349190381
SN - 9781424438112
T3 - 2009 IEEE/PES Power Systems Conference and Exposition, PSCE 2009
BT - 2009 IEEE/PES Power Systems Conference and Exposition, PSCE 2009
T2 - 2009 IEEE/PES Power Systems Conference and Exposition, PSCE 2009
Y2 - 15 March 2009 through 18 March 2009
ER -